Improving project cost estimation by taking into account managerial flexibility

Jørgensen, Trond and Wallace, S W (2000) Improving project cost estimation by taking into account managerial flexibility. European Journal of Operational Research, 127 (2). pp. 239-251. ISSN 0377-2217

Full text not available from this repository.

Abstract

Project costs tend to be higher than depicted by budgets. Irrespective of the quality of the project management, this indicates that the budgets are not established in a way which is consistent with how projects are run. Good budgets should on average lead to zero cost overruns. The purpose of this paper is to discuss how project costs (if they are based on models) can be better estimated by taking into account how projects are actually run, in particular, how managerial flexibility adds value to a project. The purpose is not to advocate better ways of running a project, but to obtain better estimates of what projects cost, given the way they are run.

Item Type: Article
Journal or Publication Title: European Journal of Operational Research
Uncontrolled Keywords: Project management ; Time-cost trade-off ; Stochastic dynamic scheduling
Subjects: UNSPECIFIED
Departments: Lancaster University Management School > Management Science
ID Code: 45381
Deposited By: ep_importer_pure
Deposited On: 11 Jul 2011 19:31
Refereed?: Yes
Published?: Published
Last Modified: 26 Jul 2012 19:15
Identification Number:
URI: http://eprints.lancs.ac.uk/id/eprint/45381

Actions (login required)

View Item